HMEL

Reactor–Regenerator Package — FCCU

Bathinda, PunjabCompleted — Mar 2012RefineryEPC / LSTK

Scope of Work

Residual design, detailed engineering, procurement and construction of the FCCU reactor–regenerator package for the Guru Gobind Singh Refinery — shop pre-fabrication of segments at Tarapur works, site assembly with welding, NDT, PWHT and hydrotesting, complete refractory lining and interconnecting flue gas duct piping.

  • Residual design and in-house detailed engineering of static equipment
  • Detailed engineering and 3D modelling of the technological structure
  • Procurement of all major bought-outs by in-house purchase department — EIL inspection (indigenous) and LRQA third-party inspection for U & R stamp activities
  • Pre-fabrication (pressing & rolling) of Reactor, Regenerator and TSS segments at Tarapur works under LRQA inspection
  • Assembly of segments, welding, NDT, PWHT and hydrotest at Bathinda site on temporary foundations built by G. R. Engineering
  • Complete refractory lining of Reactor, Regenerator, Orifice Chamber and TSS at site
  • CS large-diameter (30"–129") refractory-lined flue gas duct piping — 240 m with 18 mitre bends
  • Technological structure fabrication and erection — 2,100 MT
  • Heavy erection lifts with Demag CC-8800 (1,250 T) crawler crane

Equipment & Package Details

EquipmentTag / UnitDetails
ReactorFCCU — U & R Stamp13,000 mm dia × 68,000 mm height · SA 516 Gr 70 & SA 387 Gr 11 Cl 1
RegeneratorFCCU — U & R Stamp15,000 mm dia · SA 516 Gr 70 & SA 387 Gr 11 Cl 1
Third Stage Separator (TSS)U & R Stamp, incl. internalsSite fabricated
Orifice Chamber & Internal/Mushroom RisersLAS constructionShop fabricated at Tarapur
Technological Structure—2,100 MT fabricated & erected
Total Fabrication—1,200 MT