Scope of Work
Pre-engineering site survey, soil investigation, detailed engineering, complete supply and installation of equipment, piping, electrical & instrumentation, civil works, modularized structures, pre-commissioning, commissioning, PGTR and 3 months operational assistance.
- Pre-engineering site survey, soil investigation & GRP ground mapping
- Detailed engineering
- Complete supply and installation of all equipment, piping, electrical, instrumentation and bulk materials
- Complete supply of all civil materials and execution of civil works
- Supply of modularized structure; welding and erection of structures
- Hiring of suitable cranes for installation of equipment, piping and structures
- Statutory certifications, inspection and testing
- Painting, insulation, pre-commissioning, commissioning and stabilization & PGTR
- Plant handover and 3 months operational assistance
Equipment & Package Details
| Equipment | Tag / Unit | Details |
|---|---|---|
| C4 Hydrogenation Unit | Complete EPC | Design to PGTR and handover |